Progreso Pilipinas

Progress and updates on the latest infrastructure project in the Phillipines . Roadtrips and more!!
Covering mostly projects of:
INFRASTRUCTURE AND DEVELOPMENTS IN CAVITE
CALAX
CAVITE LAGUNA EXPRESSWAY
SKYWAY
SLEX
SOUTH LUZON EXPRESSWAY
SLEX TR4
MRT
LRT
METRO MANILA SUBWAY
BYPASS ROADS
DIVERSION ROADS
TOWNSHIP PROJECTS
AIRPORTS
MEGA CITIES
and more projects under the BUILD BUILD BUILD program of the Government under the supervision of the DPWH and DOTR.

FACEBOOK PAGE:
PROGRESO PILIPINAS


Progreso Pilipinas

Happy Independence day!

1 year ago | [YT] | 11

Progreso Pilipinas

CALAX IB4 is now open!
Imterchange bridge 4 at Aguinaldo highway, Silang Cavite.

1 year ago (edited) | [YT] | 8

Progreso Pilipinas

Girder installation CALAX CAVITEX LINK at Antero Soriano highway Kawit, Cavite.
A 1.2km viaducts along the highway for a seamless connectivity of CALAX and CAVITEX.

1 year ago | [YT] | 16

Progreso Pilipinas

Thankyou sa inyong lahat mga Paps at umabot na tayo sa 16k subs! More updates to come!

1 year ago | [YT] | 13

Progreso Pilipinas

Calax-Cavitex link. Konti pa at pwede na lagyan ng girders ito.

1 year ago | [YT] | 12

Progreso Pilipinas

Happy New Year mga Paps!

1 year ago | [YT] | 12

Progreso Pilipinas

CALAX subsection 1 or the Kawit interchange

Subsection 1 will run from the open canal area in Imus and end in Antero Soriano highway in Kawit, Cavite. It has an estimated length of 8.68 km, with construction currently at 26% completion and 77% of the right-of-way (ROW) acquired. It is expected to be finished by Q3 of 2025.

Along the route of subsection 1, landmarks such as the new city hall of Imus, The MPT Southhub and the historic Alapan Heritage Park will be visible. The section will end in Kawit, where it will exit at the Evo City development by Ayala and will end at the Antero Soriano highway.

In the Kawit area (Toclong), viaducts will be constructed running atleast 700m of viaducts to link this section to Cavitex, which is also currently under construction.

1 year ago | [YT] | 17

Progreso Pilipinas

CALAX subsection 2 also known as the Opencanal interchange is a 9.86km expressway making it the longest interchange of all the 8 segments of CALAX.
It will run from Brgy. San Francisco in General-Trias Governors drive all the way to Imus Opencanal or the Daanghari extension.
The alignment will pass through two of the township developements in Cavite; Riverpark south and north and the Lancaster new city.
Target completion date is on Q3 of 2025 and it is now at 16% construction rate percentage with 75% ROW acquired.

1 year ago | [YT] | 12

Progreso Pilipinas

CALAX Governors drive interchange subsection 3 is now at 25% completion rate with 98% ROW acquisition and is targeted to open on the first quarter of 2025.
Subsection 3 a 8.64km alignment from Governors drive to Aguinaldo interchange.
You can watch the full details of the CALAX construction update on my Youtube channel.
https://youtu.be/m4gR-MhvU_k

1 year ago | [YT] | 13

Progreso Pilipinas

Construction update for CALAX sub-section 3-2 and 1.

FAQ's
•Sub-section 3 target opening: 1st Quarter 2025
•Will there be any added toll fee for the CALAX-CAVITEX Link: No additional fee

Thanks MPT Southhub for the invite.

Palabas naten ang full tour sa Youtube mga paps!

1 year ago | [YT] | 19